energy · the national build-out

Britain’s clean power build-out

Every renewable and low-carbon power project in Britain's planning database, from the Renewable Energy Planning Database. This is the build-out: what is operating, what has consent and is waiting to be built, and what is still in planning, by technology, company and nation. 57.0 GW is operational, with far more in the pipeline.

How to read this

The Renewable Energy Planning Database tracks projects above 150 kW through planning, from application to operation. It is a record of the pipeline, not a measure of electricity generated. Capacity is installed megawatts, not the power actually produced, which depends on the wind and the sun.

Every figure is computed from the published database, the Q1 2026 extract with records updated to April 2026. Project locations come from the grid reference on each record.

57
GW operating
140.7
GW awaiting construction
14,316
projects tracked

The pipeline

Built, being built, and waiting

57.0 GW of clean power is operating today. Another 140.7 GW already has planning consent but has not been built, the single biggest block in the pipeline, which points at grid connection and finance rather than planning as the hold-up.

Operationaloperating now
57 GW3,100 projects
Under Constructionbeing built
21.9 GW436 projects
Awaiting Constructionconsent granted, not yet built
140.7 GW5,597 projects
Application Submittedin planning
88.3 GW1,684 projects
Application Refusedrefused
17.7 GW900 projects

The mix

What is generating now

Operational capacity by technology. It is a broad mix: onshore and offshore wind and solar lead, but battery storage, biomass, pumped storage and hydro all feature.

Wind Onshore
15.3 GW778
Wind Offshore
15.1 GW48
Solar Photovoltaics
10.9 GW1,393
Battery
4.8 GW171
Biomass (dedicated)
3.5 GW81
Pumped Storage Hydroelectricity
2.8 GW4
EfW Incineration
1.5 GW60
Landfill Gas
0.8 GW270
Biomass (co-firing)
0.7 GW2

Across the nations

Where the operating capacity sits

Operational capacity by nation. England has the most in total; Scotland carries a large share for its size, with onshore wind to the fore.

England
34.1 GW2,150 projects
Scotland
16.2 GW583 projects
Wales
5.3 GW247 projects
Northern Ireland
1.5 GW118 projects

Year by year

How fast it has been built

New operational capacity added each year. The pace has been uneven, and the recent years sit below the middle of the last decade even as the consented backlog has grown. The 2026 figure covers the first quarter only, as far as the extract reaches, so it is not a full year.

GW of new operational capacity added each year. 2026 is a partial year. Source: Renewable Energy Planning Database.

Who builds it

The biggest operators

The companies with the most operational capacity. A handful of large developers, several of them offshore wind specialists, account for a big share.

1.Orsted (formerly Dong Energy)
4.4 GW13 sites
2.Drax Power
2.6 GW4 sites
3.First Hydro Company
2.1 GW2 sites
4.Scottish Power Renewables
1.9 GW21 sites
5.Scottish and Southern Energy (SSE)
1.7 GW55 sites
6.Vattenfall
1.1 GW11 sites
7.SSE / Seagreen Wind Energy Ltd
1.1 GW1 sites
8.Diamond Green Limited, CTG & Ocean Winds
0.9 GW1 sites

Close to home

The build-out in West Lothian

West Lothian has 53 projects in the database, 0.9 GW in all, of which 0.1 GW is operating. The striking local trend is battery storage: 11 of the 53 are battery projects, alongside onshore wind such as Tormywheel and Longhill Burn. The county is becoming a place where power is stored as well as made.

53
projects
0.9
GW total
0.1
GW operating
11
battery projects
SiteTechnologyMWStatus
Pond Industrial Park, Whitburn Road - Pond Battery StorageBattery200Awaiting Construction
Drumshoreland Road Battery Storage FacilityBattery49.9Awaiting Construction
Middlerigg - Battery Energy StorageBattery49.9Awaiting Construction
Fauch HillWind Onshore48Appeal Refused
Longhill Burn Wind FarmWind Onshore45.6Under Construction
Gladsmuir Hills - Wind FarmWind Onshore41Application Submitted
Leyden Road - Solar ArraySolar Photovoltaics40Application Submitted
TormywheelWind Onshore30.8Operational
Drumcross Battery StorageBattery30Awaiting Construction
Learielaw FarmBattery29.9Revised

Questions this raises

For developers, the grid and government

  1. 1.

    140.7 GW has consent but is not built. Is the grid connection queue, not planning, now the real constraint on clean power?

  2. 2.

    Battery storage is the fastest-growing category, locally and nationally. Is the planning and grid system keeping pace with storage as well as generation?

  3. 3.

    New operational capacity in recent years sits below the middle of the last decade. What would it take to build the consented pipeline out faster?

  4. 4.

    A small number of large developers dominate. Is there room for more community and locally owned schemes?

Sources & method

Data provenance

Caveats & data notes

  • The database tracks projects above 150 kW through planning. It is a pipeline record, not a measure of electricity generated.
  • Capacity is installed megawatts. Actual output depends on the technology and the weather, so a megawatt of solar and a megawatt of gas are not the same in practice.
  • Status reflects the latest planning stage recorded. The pipeline shifts each quarter as projects progress, are refused or are abandoned.
  • West Lothian projects are identified by the county and planning authority fields.
  • Contains public sector information licensed under the Open Government Licence v3.0.